Bridge Work on I-93 in Manchester

Southbound work will affect traffic at Exit 7 throughout the summer

The New Hampshire Department of Transportation (NHDOT) announces anticipated lane reductions for bridge work on I-93 southbound in Manchester beginning on Sunday, June 6, 2021 at 8 pm.  Southbound traffic will be reduced to two lanes at Exit 7 to allow construction crews to perform concrete repairs and install new expansion joints on the bridge over Stevens Pond.  Set up work will continue Monday night from 8 pm to 5 am, and the lane restrictions will be in place through the summer.

Slower traffic may be encountered through the work area.  Motorists should remain alert while traveling through the construction zone and obey all posted signs.

This $8.4 million bridge preservation project is being constructed by R.S. Audley, Inc from Bow, NH.