Nighttime Work at Exit 2 on I-95 in North Hampton
This work will require temporarily close the northbound Exit 2 off ramp overnight.
The New Hampshire Department of Transportation (NHDOT) will continue work to rehabilitate the I-95 Exit 2 bridge in North Hampton on Wednesday, October 12, 2022. The work will require the northbound Exit 2 off ramp to be closed temporarily at night from 9 pm to 5 am.
Weather permitting, construction crews will close the ramp in order to move barrier and place new striping across the bridge.
Detour signing will be in place to direct motorists around the closure. Motorists should remain alert while traveling through the construction zone and obey all posted signs.
This work is part of the North Hampton 42979 project. New England Infrastructure of Hudson, Massachusetts is the prime contractor for the $4.9 million project, which is scheduled to be completed in November 2023.